Posted on: August 1, 2018

Road Construction Projects

Construcation Projects

October 30 UPDATES IN GOLD

Whites Road - Road Restoration Project

Valley Forge to Broad St.

Lane
closures thru 10/31

Road Closed
11/1 & 11/2 (Weather Depending)
Laneclosures 11/2 thru 11/9 for pavement markings

North Line Street - Road Restoration Project

E. Main St to Borough/ Hatfield border at Oak Drive.

Uneven Paving - No closures at this time

W Third Street - Road Restoration Project

Valley Forge to Cannon Ave.

Closures expected in coming weeks while sewer upgrades are completed.

road closed during working hours Monday - friday

E. Hancock - NPWA Water Main Renovation Project

Church Rd to Broad St.

The east bound lane will be closed M-F 7 am - 4 pm

There will also be intermittent road closures expected for the next several weeks.

E Hancock St to be paved this fall as part of the mill and pave projects.

no closures at this time

Mill and Paving Projects

Courtland (Richardson to Green)

E. Hancock (Broad to Church)

S. Cannon (Main to Whites Rd.)
Intermittent road closures in upcoming weeks while road repairs, corner ramp replacement and new paving are completed.


Montgomery Ave (Vine to E. Hancock)  COMPLETE
Ongoing, intermittent lane closures while corner ramps are rebuilt


Micro Surface Projects

W. Mt. Vernon Street (Broad to Valley Forge)

Rescheduled due to rain


Delaware (Susquehanna to Cannon Avenue)

Rescheduled due to rain

Green (Main to Whites Road)

Complete

Lincoln (Broad to Green)

Complete

Susquehanna (Main to Whites Road)

Complete

Jefferson Street

Complete

Hamilton Street

Complete

Franklin Street

Complete

Jackson Street

Complete

Intermittent road closures in upcoming weeks while road repairs and new surfacing are applied.  Ongoing daily closures, roads may be closed during work hours. 


Underground Utility Project between Madison and Walnut Streets

In the upcoming weeks, utility work in this area will require a short term closure of Walnut street between Third and Main Streets.

For several months parking will be blocked along Walnut Street in the vicinity of the Main Street intersection. 

there may be short term closure through November 9 for final paving



Facebook Twitter Google Plus Email

Other News in Lansdale Spotlights

Council Vacancy

Council Vacancy to Be Filled

Posted on: December 6, 2018
2019 Budget 2

Borough Budget and Financial Dashboard

Posted on: October 7, 2018